| Project Code: | C208772144 | Site Status: | Active |
| Site Name: | LORAC COMPANY (G&M) |
| CERCLIS Number: | |
| Other Names: | |
| Address: | 624 EAST HARRY STREET | City: | WICHITA |
| Zip Code: | |
| County: | SG | River Basin: | Lower Arkansas |
| Latitude: | 37.66453 | Longitude: | -97.331 |
| Program Name: | BER - State Cooperative | Project Manager: | Injal Bhattarai |
| Contaminants: | VOC |
Environmental Use Control In Place ?
No
|
We are currently experiencing technical difficulties with requests for some documents. If an attempt to download an individual document from the “Documents/Photos Available” link does not return the expected results, please contact the Project Manager associated with the Identified Site or the Remedial Section at 785-296-1660. We are working to resolve this problem as quickly as possible and apologize for any inconvenience this may cause.
Documents/Photos Available
(Opens in New Window) |
|
|
Site Narrative:
Volatile organic compounds (VOCs) were detected in a pair of nested monitoring wells as part of the Gilbert and Mosley quarterly sampling beginning in June 2003. The monitoring well pair was installed in February 2002 as compliance wells between Plumes A, B and E. Concentrations of tetrachloroethylene (PCE) increased until September 2004 to a maximum of 4400 micrograms per liter (µg/L). KDHE and the City of Wichita conducted a series of ground water sampling events to determine the source of VOC concentrations in the well pair. Significant concentrations were detected in sampling points on the Lorac property, while no concentrations were detected upgradient of the property. Additional sampling was conducted to attempt to define the down-gradient extent of the contamination.
In the summer of 2008, Lorac agreed to the terms of a KDHE letter agreement. They have retained Shaw Environmental to perform a site investigation. A limited site investigation commenced in July 2009.
The City of Wichita has taken over the remediation of the Site under the 1991 Consent Order for G&M. Consultant selected for additional investigation of source areas at site. The first phase of the CI/CAS was completed in March 2018. The second phase was performed in August 2018. |
|
|
Legal Description
|
No Legal Description Information Found
|
|
|
|
Actions Completed
| PUBLIC RELATIONS | Community Relations Plan | 11/01/1991 | 11/01/1991 |
| ASSESSMENT | Site Inspection (SI) | 01/06/2004 | 01/06/2004 |
| PRP IDENTIFICATION/NEGOTIATION | Information Request Letter | 05/24/2005 | 05/24/2005 |
| ASSESSMENT | Site Assessment | 05/10/2005 | 10/03/2005 |
| ASSESSMENT | Preliminary Assessment (PA) | 07/27/2009 | 07/27/2009 |
|
|
|
Actions Underway
| MASTER PROJECT | Master Project Details | 11/01/1991 | |
| INVESTIGATION | Comprehensive Investigation | 04/03/2018 | |
|
|
|
Actions Proposed
|
No Actions Proposed Information Found
|
|
|
|
Map of Identified Site ((One-mile radius circle around selected site))